Friday, 26 March 2010

The End

I finished evaluating the development of the system. At the start of July, interation will take place and the system life cycle will start all over again, with the improvement and extensions included (as mentioned in the evaluation).

Thursday, 25 March 2010

Starting Evaluation

I've completed two user guides for both registered users and administrators.
Now that I've completed the plans for installation, I'm going to start evaluating the project.

Saturday, 20 March 2010

Training and User Guides

I had a discussion with my client yesterday and we decided that the staff should undergo training and a user guide should be typed up. I need to make two user guides, one for registered users and one for the administrators.
I've started creating the user guide for the registered users.

Monday, 15 March 2010

Installation

The improvements have been made and the system seemingly works as hoped for (except for the features that have been missed out due to lack of time).
I now need to plan how the staff of MDU are going to learn to use the system.

Saturday, 13 March 2010

Improvements

I've completed the test plan, I'm now starting with the system amendments and re-testing.
There were 8 out of 41 unsuccessful tests.